Building C
Planned hospital building
Building
C is ment to be some sort of evaluation hospital while building A and B are
restored and after that a badly needed complement to the two other buildings.
The
alternative is to close the maternity hospital during the construction time
about 1,5 year or to find enough places for the patients at hospitals in other
cities.
Building C – with 40 rooms for
different inability inclusive 50 beds for patients – would be just what dr
Lydia need for her activities at the maternity hospital.
Glaves for once only use
are washed and dried…
This is also a way
to sterilize…
Most of the
pregnant women are in such a bad shape during their pregnancy,
that they need
special treatment in hospital.
Economic
calculation
Conditions
At
the time (2003-02-20) it is impossible to make a real budget.
A
real budget demands, that we can be in Novozybkov long enough to be able to do
it with the help of Russian experts. We therefore assume:
1)
the economical calculations from the hospital.
2)
the knowledge that we have within the project concerning building technique and
economy
(Gunnar Sundqvist) and
3)
the cost that we already paid for the roof of building A (30 000 SEK) which can
be put in relation to
other normal costs for building material
and services.
Restoring A and B
Both
buildings have an area of about 775-800 square meters. They are built of stonse
and shall practically be blown out, which means new floors, new windows, new
furnishing, new electrical installations, new water and outflow installations
and for building B a new roof.
The
Russians mean that the cost for that is about 500 000 crowns or 925
crowns/square meter. That shall be compared with the normal Swedish cost of 12
000 crowns / square meter.
As
far as we know (2003-02-20) the restoring of A and B will cost about 1 million
crowns.
Construction of building C
Building
C, that is as big as A and B, is a prerequisite before restoring A and B.
Otherwise the patients have to be evacuated to other cities. One of them is
Klincy about 70 kilometre from Novozybkov, where most people do not have their
own car.
The
total cost to build C is about 6 447 000 rouble which is the same as 2 million
13 000 crowns.
The
work will take 2 760 hours/man or 1,46 year for 10 workers. To that comes 8
months for projecting the building.
Finance
Alternative I
The
project ask for 1 million SEK to renovate the buildings A and B and 0,5 million
SEK to exchange furnishing and medical equipment. This includes costs for
administration, travels, transports, documentation and so on.
Total
cost 1,5 million SEK.
The project ask all Lions Clubs in Sweden to pay 65
crowns per member, which will be 14 700 x 65 SEK = 955 500 SEK. We also have
hope for a grant of 75 000 USD from Lions Clubs International Foundation
(LCIF).
Alternative II
The
project ask for 3 million SEK to construct building C (2 million SEK) and
renovate buildings A and B (1 million SEK) and 0,5 million SEK to exchange furnishing
and medical equipment. This includes costs for administration, travels,
transports, documentation and so on.
Total
cost 3,5 million SEK
The project ask all Lions Clubs in Sweden to pay 65
crowns per member during three years, which will be 14 700 x 65 SEK = 955 500
SEK per year or 2.866.500 SEK. We also have hope for a grant of 75 000 USD from
Lions Clubs International Foundation (LCIF).
Service in return (from Novozbykov)
The Administration of Novozybkov
shall, as a service in return to the Swedish Lions Clubs, renovate the
laboratory building east of the buildings A-C.
The
Administration also have to – to minimize the risk for further infection -
build a special clinic for HIV-infected, pregnant women.
How to carry out the project
Goal I
The goal of the project is to on the first hand
collect 3 million SEK (3 years) or on the other hand 1 million SEK (1 year) so
that:
1) C can be built and A-B renovated or
2) A-B can be renovated.
We are going to ask for economic support from
different authorities and/or organizations.
Goal II
The project will be presented to the Governors
Council Meeting in February 2003 and for the Swedish convention at the end of
May 2003. Hopefully the project from 2003-07-01 will be a question for the
multi district 101 Sweden.
The project ask all Swedish Lions Clubs to pay 65
crowns per member during one or three years. All Swedish Lions clubs shall also
get the possibility to get their own mini-project within the Lions project
Children of Chernobyl / Novozybkov.
Goal III
At the end of 2003 the multi district 101 Sweden
will ask for a grant from Lions Clubs International Foundation (LCIF) with 75
000 USD.
Goal IV
The last goal is to if possible use funds from Core
4 to education of the hospital staff in Novozybkov.
Who will be
concerned
All Lions Clubs in Sweden.
The project will even ask for support from for
example the Swedish church, community, authorities and other humanitarian aid
organizations.
How to realize
the project
Representatives for the project have opened
discussions with responsible persons in Novozybkov in order to realize the
project.
An
agreement have been signed with the mayor, the Savings Bank of the Russian
Federation and LC Vallentuna. Money can therefore be sent to the maternity
hospital with no risk.
Each
payment demands 1) a specified verification, 2) sign by dr Lydia, 3) signed by
the mayor and 4) sign by Anders Rönnholm (who wrote the agreement).