Maternity
Hospital building 1
The budget
is based on an offer from Russian building –contractor and controlled by
Medical Department in Brianska region.
*
|
New Cold
and hot water system, sanitary installations
|
792.000:-RUB
|
*
|
Inside
Renovation floors, walls, roof, the putty works windows
|
984.600:-RUB
|
*
|
New
linoleum
|
205.300:-RUB
|
*
|
The
ceramics and ceramic work
|
585.600:-RUB
|
*
|
Civil
works inside
|
387.700:-RUB
|
*
|
New
electrical installations
|
622.900:-RUB
|
|
|
|
*
|
Total
cost for building 1
|
3.578.100:-RUB
|
*
|
WAT
|
-537.700:-RUB
|
|
|
|
*
|
Total
cost for building 1 without WAT 18 %
|
3.040.400:-RUB
|
|
|
|
*
|
Total
cost in SEK Rate 0,28 (Rate of risk
10 % is included for SEK
|
851.312:-SEK
|
.
Maternity
Hospital gynaecological department, building II
The budget
is based on an offer from Russian building-contractor but is not controlled by
some control organization.
*
|
Renovation
of, hot and cold water system, sewerage, electricity system
|
1.060.200:-RUB
|
*
|
Renovation
of floors, walls, roofs, windows, doors
|
886.100:-RUB
|
|
|
|
*
|
Total
cost for building II
|
1.946.300:-
|
*
|
WAT
|
-292.300:_RUB
|
|
|
|
*
|
Total
cost for building II without WAT 18 %
|
1,654.100:-RUB
|
|
|
|
*
|
Total
cost in SEK Rate 0,28 ( Rate of risk 10 % is included for SEK
|
463.200:_SEK
|
Materninty
Hospital building I and II
Budget
based on building I and II included, travels, printed matter and administration
cost.
*
|
Building
I
|
3.040.400:-RUB
|
*
|
Building
II
|
1.654.100:-RUB
|
*
|
Travels,
printed matter and administration cost
|
541.500:-RUB
|
|
|
|
*
|
Total
cost for building I and II
|
5.236.000:-RUB
|
|
|
|
*
|
Total
cost in SEK Rate 0,28 ( Rate of risk 10 % is included for SEK
|
1,466.080:-SEK
|