Application 2 Project plan


Project plan

The Lions Project Children of Chernobyl / Novozybkov
The project plan was originally written by Monica Antonsson, Anders Rönnholm and Gunnar Sundqvist, Lions Club Vallentuna, district 101-U, Sweden, 2003-02-20 - Se page 201.
See also current project plan, page 12.

Goal
Our goal is to give dr Lydia Vladimirovna Bavkunova and the women of the radioactive polluted town Novozybkov in Russia the best possible maternity hospital where life begins. The health of newborn children and their mothers are of great importance to the future.

History
The project was originally born in LC Vallentuna. At the time for the project plan 2003-02-20 it was a project within district 101-U. However, the plan was written to make it a multi district project for all Lions Clubs in Sweden. It offered two possible alternatives:
1) to restore the two buildings A and B and to build a new building C or
2) to restore the two buildings A and B.
In both cases we plan to furnish the buildings and exchange existing medical equipment to more modern equipment from Sweden or elsewhere.  

At the Swedish Convention in Piteå in May 2003 the project was accepted as a multi district project. Alternative 2 was chosen. All Swedish Lions Clubs were recommended to make a contribution of 65 Swedish crowns (SEK) per member in order to collect 1 million SEK. From the start there were also plans for a Grant Application to LCIF.

Some pictures from the Swedish Convention in Piteå 2003:






We were very happy to welcome our International president (2002-2003) Kay K Fukoshima 
to our exhibition about the Lions project Children of Chernobyl / Novozybkov.



Project management

Lions Clubs district 101-Sweden


Monica Antonsson


Anders Rönnholm


Bruno Pettersson


Roger Larsson

Project manager: Monica Antonsson, LC Vallentuna
Vice project manager and economy: Anders Rönnholm (pp), LC Vallentuna
Expert advisor: Bruno Pettersson (pp, pird), LC Norrköping
Transport manager: Roger Larsson, LC Vallentuna
Expert advisor: Conny Kingfors (pp), LC Täby
Photographer: Leif Bäckström (pp), LC Täby
Assistant: Liselotte Lindberg, LC Vallentuna
Assistant: Roland Jansson, LC Vallentuna



Project management in Novozbybkov


Ivan Nesterov


Lydia V Bavkunova


Inna Skvortsova


Larisa Kayushnikova

Mayor Ivan Nesterov, Novozybkov, the head of the Administration of Novozybkov
Dr Lydia Vladimirovna Bavkunova, Chief physician, medical superintendent
Valentina Anikeeva, chief manager of the Saving Bank of Novozybkov
Inna Skvortsova, chief of the Capital Construction of the Department at the Administration
Larisa Kayushnikova, responsible at the main architect office at the Administration
Tamara Roschkova, interpreter
Vitaly Roschkov, responsible for the Chernobyl questions at the Administration in Novozybkov



The project


The project aims at restoring two existing buildings A and B within the Maternity hospital in Novozybkov, Bryansk region, Russian Federation.

At the Swedish Governors Council in Denver, Colorado July 1, 2003, Monica Antonsson officially became the project manager and Anders Rönnholm the vice project manager responsible for the projects economy - See page 251-254.

As a consequence – and after detailed instructions from past IRD Bruno Pettersson, Monica Antonsson and Anders Rönnholm went to Novozybkov, where agreements were signed with:
1) major Ivan Nesterov
2) dr Lydia Vladimirovna Bavkunova
3) the local Savings Bank
4) the Tax authority and
5) the Medical Department in Bryansk.
See: page 33 and following pages.

Thanks to that we:
1) have full control over whatever humanitarian aid we in the future will send to Novozybkov.
    The mayor agreed that we have the right to decide every detail of the project, where to put
    humanitarian aid gifts and so on.
2) have a very close cooperation with dr Lydia whom we really trust. In fact we are in
    touch with her by e-mail and telephone almost every day.
3) have got a so called dollar-account at the local Savings bank, which makes it easier to transfer
    money. Dr Lydia is the only one who can get money out of the account – after both mayor
    Nesterov and Anders Rönnholm have sign the papers.  
4) are free from WAT taxes within the amount 3 700 000 roubles, which means that we do not
    have to pay the 18 per cent taxes on for example building material. This is a unique decision
    made as an exception for the first time in Russia. It took several visits and meetings with the
    authorities in both Bryansk and Moscow to get it. 
5) have full a trustable control authority on our side. A representative from the medical department
    lives in Novozybkov during the building time. He makes observations and sends regularly
    reports to us of how the work is going on. If he thinks, that the work is badly done, he is in
    position to stop it.

Economy


Our plan is to finance the project with contributions from every Lions Clubs Sweden with SEK 65 for each member, money as gifts from other organizations, from private persons and from activities in Lions Clubs Sweden. We will also apply for a standard Grant from LCIF.


Buying contractors/Budget/estimate costs


The buying of renovation has been done through official buying in Bryansk region according to Russian rules for buying. Costs estimates have been received, analysed and compared of the administration in Novozybkov, the Maternity Hospital in Novozybkov and the control organization Medical department in Bryansk. One of the most important points in this buying was that the contractor must do the renovation during 75 days without lower one's standards of quality. The hospital must be evacuate and closed for 75 days during the renovation and all patients must go to other Maternity Hospitals in Bryansk region, (town Klintsy and Klimova about 70 kilometres from Novozybkov). Agreement between Maternity Hospital Novozybkov and the Contractor is controlled by the administration of Novozybkov and Medical department in Bryansk region.





Maternity Hospital building B

Budget/estimate costs


*
New Cold and hot water system, sanitary installations
792.000:-RUB  
*
Inside Renovation floors, walls, roof, the putty works windows
984.600:-RUB
*
New linoleum
205.300:-RUB
*
The ceramics and ceramic work
585.600:-RUB
*
Civil works inside
387.700:-RUB
*
New electrical installations
622.900:-RUB



*
Total cost for building B
3.578.100:-RUB
*
WAT
-537.700:-RUB



*
Total cost for building B without WAT 18 %
3.040.400:-RUB



*
Total cost in SEK   Rate 0,28 (Rate of risk 10 % is included for SEK
851.312:-SEK





 

Maternity Hospital gynaecological department, building A



The budget is based on an offer from Russian building-contractor but is not controlled by some control organization.


*
Renovation of, hot and cold water system, sewerage, electricity system
1.060.200:-RUB
*
Renovation of floors, walls, roofs, windows, doors
886.100:-RUB



*
Total cost for building A
1.946.300:-
*
WAT
-292.300:_RUB



*
Total cost for building A without WAT 18 %
1,654.100:-RUB



*
Total cost in SEK Rate 0,28 ( Rate of risk 10 % is included for SEK
463.200:_SEK


Maternity Hospital building B and A


Budget based on building B and A included, travels, printed matter and administration cost.

*
Building B
3.040.400:-RUB
*
Building A
1.654.100:-RUB
*
Travels, printed matter and administration cost
541.500:-RUB



*
Total cost for building B and A
5.236.000:-RUB



*
Total cost in SEK Rate 0,28 ( Rate of risk 10 % is included for SEK
1,466.080:-SEK

 



Agreement between Maternity Hospital Novozybkov and the Contractor is controlled by the administration of Novozybkov and Medical department in Bryansk region.

After a lot of discussion with different control organization we decided to choose Medical Department in Bryansk. Our intentions were to find a control organization witch in a proper way could do all controls in an impartial way. Medical department is a control organization who has by direction to control the construction of all new hospital building and renovation of old hospitals. They should also control private contractors.



Lions Clubs International Sweden and Medical department Bryansk has signed a Cooperation Agreement between each other.
-        Control of the contractor’s estimate costs, of the timetable and of the payment term
-        Control that the contractor follow the regulation of technical and quality for the renovation
-        Control inspection of performed work must be done according to every 500.000:- roubles
-        Every invoice shall be controlled against performed work to every 500.000:- roubles
-        Control of agreements between MH and the contractor
-        Control inspection of material delivered before the renovation 2004-03-01
-        If MD don’t accept the performed work, MD have the possibility together with LMD to stop the work with the contractor
-        Solidity control of the contractor
-        Final inspection must be done before 2007-07-15
-        All information shall be written in English
-        Every control shall be signed by MDB and send to LCMD.


WAT


Lions Clubs International Sweden has as a demand that we not shall pay any WAT. Together with Maternity Hospital we began to discuss with the local tax authorities that we shouldn’t pay any WAT. Unfortunately they rejected our application. Next instance we send our application to, was the region Bryansk tax authorities, also they rejected our application but they send our application to the government in Moscow (tax authorities commission for Russia) After one month and lot of contacts with the tax authorities commission and also the commission for Humanitarian aid in Russia the decided together to give us liberation not to pay any WAT for all materials we bye for our project.


Money transferring between Lions Clubs International Sweden and Maternity Hospital


All transferring of money is regulated by an agreement between Maternity Hospital Novozybkov Chief Doctor Lydia Bavkonova and Lions Clubs International Sweden.
Lydia Bavkonova and a responsible person from the contractor shall sign all invoices and send the invoices by fax to Lions Club International Sweden for sign.

Fore each 500.000 roubles there must be two different controls:
-        The invoices against used material and hours of work
-        The performed work.

Lions Clubs international Sweden will send money to an account in The Saving Bank of the Russian Federation (Branch Novozybkov).

More details see the bank agreement - see page 52.



Time table

Building B
The renovation of Building B (the white maternity hospital) started March 10, 2004 and will be finished July 1, 2004.

Building A
Building A (the red gynaecological clinic) is planned to be restored during September 2004 – January 2005, if we get the Grant from LCIF.



Furniture and medical equipment
When it comes to furnishing the buildings with both furniture and medical equipment we now cooperate with the Salvation Army in Västerås, Sweden. The reasons is that 1) we have no storehouse anymore (it takes four months to get each transport acknowledged as humanitarian aid and free of charge), 2) the Russian laws have changed which have made the administration of each transport very hard and 3) the prize for a long distance truck transport to Novozybkov has raised with 35 per cent to 35 000 SEK.

It is still profitable to send medical equipment but probably not furniture. LC Vallentuna therefore ordered 80 brand new, Russian hospital beds of stainless steal with as many tables/cupboard
to a price less than what the transport of 60 second hand hospital beds from Sweden would cost. As it seams now, it is better for us to collect money and buy the furniture in Russia. However,
Furniture and medical equipment have nothing to do with the project. The project is only about the restoration of buildings A and B.



Inspections

 Due to our agreement with the Medical Department in Bryansk (MDB) – See page 46 - they will, during 2004-03-01 – 2004-06-30, carry out regularly inspections of the work at Building B, each time the total cost passes 500 000 roubles. They have if necessary the right to stop both the work and the contractor. After each control they are sending reports to the project management in Sweden. See page 18 and/or 50.
A final inspection shall be done before 2004-07-15.

When it comes to Building A we will ask for similar agreements.



Final statement
When our undertakings are fulfilled, we will of course not just leave it and forget about it. We will try to somehow get the best medical equipment and furniture on at first hand club level. That means that we will work hard in LC Vallentuna and encourage other Swedish clubs to do the same. Thanks to that we will during a foreseeable future have the possibility to regularly follow up what happens at the Maternity hospital in Novozybkov.

Hoping that the District-assembly will make a positive decision and will sanction the Lions project Children of Chernobyl / Novozybkov, we hereby finish our pledge with the Motto of Lions Clubs International:

We Serve!


Vallentuna, Sweden 2004-04-25



Monica Antonsson                                                         Anders Rönnholm
Project Manager                                                            Vice Project Manager
Bällstavägen 55 B                                                          Gårdsvägen 12
186 50  Vallentuna                                                        186 94  Vallentuna
Sweden                                                                           Sweden

Tel: +46-8-511 747 71                                                   Tel: +46-8-512 402 11
Fax: +46-8-511 728 24                                                  Fax: +46-8-512 403 11
Mobile: +46-705-93 09 57                                            Mobile: +46-708-68 12 16